Woodrush High School, Birmingham

Redundant school plant room strip out project.

Do you have a project like this coming up?

Project

Information

Package Value

£10,000

Duration

2 Weeks

Sector

Services

Challenges, Restrictions & Equipment

At Woodrush High School, Birmingham we were employed to remove two congested plant rooms which consisted of water tanks, pumps, boilers and all associated pipework and fittings. Even being such a small 2-week project which had to be performed over two phases, it had its challenges such as a matrix of live services that had to remain live. Our site team had to use their experience and initiative to improvise suitable techniques whilst still remaining able to work extremely safely and in a professional manner. Zero disruptions to the school, another happy client.